Hume and Merri-bek Sewer Improvement Works

In 2014/2015, we completed a detailed condition assessment of 284 maintenance holes in the Pascoe Vale sewer catchment. This assessment, part of our proactive maintenance inspection program, identified 112 sites that required rehabilitation.

The rehabilitation works involved:

  • Relining maintenance holes at 147 sites
  • Recoating or replacing lids at 139 sites
  • Replacing drop pipes at 24 sites
  • Removing ladders/iron steps at 110 sites.

In 2018, our Project Partner, Interflow, inspected a further 43 maintenance holes and rehabilitated 35 sites. 

Relining maintenance holes
Before lining

 

Contact details

If you have any construction-related questions during these works, please contact Interflow's construction manager, Scott Smith, on 9212 6700 or 0437 599 384 during business hours.

For any other questions or feedback about this project, please contact Yarra Valley Water's project manager, Derheta Wagenaar, on 9872 1715.