Wollert Recycled Water Project

We constructed new recycled water pipes in Wollert in 2017 and 2018 to ensure future residential developments in Epping North, Wollert, Mernda and South Morang can receive a reliable supply of recycled water.

Project details

Between June 2017 and March 2018 our contractor, Kaycee Excavations, built the new recycled water pipe within the nature strip, under footpaths, and within the service lane along the north side of Harvest Home Road (between Edenvale Boulevard and Epping Road), as well as within the service lane (between Redrock Road and Silverstone Circuit).

We planted new trees to replace those that needed to be removed as part of the works, and have repaired most affected nature strips, footpaths and road surfaces.

The following road and footpath surface repairs were completed by June 2018:

  • Damaged road surface in the service lane between Redrock Road and Silverstone Circuit
  • Damaged road surface across Champion Parade, and the footpath and rock pavement between Champion Parade and Epping Road.
Map of where new pipes were built
The blue line shows where the new pipe was built.

Contact us

If you have any questions or feedback about this project, please contact the project manager, Aaron Kee, on 9872 1606 or email [email protected].

 

New recycled water facility at our 521 Craigieburn Road East site

We're planning to upgrade our existing recycled water treatment plant at our Craigieburn Road East site. 

More information