Chevron RightCredit CardFacebookGoogle PlusInfoInstagramLinkedInLockPhonesearchTwitter

Craigieburn Sewage Transfer Hub Project

Yarra Valley Water is constructing new sewerage infrastructure in Craigieburn to improve our capacity to collect, store and transfer sewage flows from future developments in Melbourne’s northern suburbs.

Critical new sewerage infrastructure is being built on our land next to the existing Craigieburn Sewage Treatment Plant, located east of Sydney Road, and south of Craigieburn Road East, in Craigieburn.

Construction details

Our contractor, CPB Contractors, will construct new infrastructure including two new above-ground tanks, a new sewage pumping station, and associated pipework and channels.

Updates

  • October 2017

    Since earthworks were completed in mid-2017, truck movements to and from the site along our temporary access road have reduced.  Delivery vehicles and concrete trucks will continue to access the site from time to time.

    CPB Contractors are currently constructing the concrete structures, tanks, buildings, pipelines and permanent access roads.

    Within the next few months, large aluminium roofs, which may be visible from a distance, will be lifted onto the tanks.

    Workers putting bolts into a storage tank
    Over 30,000 bolts will be used in constructing this storage tank
    Workers fixing steel for the drop structure
    Steel fixing on the Drop Structure
    Panorama of the construction site
    The construction site (L-R: storage tanks, drop structure, and inlet structure

     

  • April 2017

    Work started in early November 2016. The most noticeable part of our works is still the high frequency of truck movements along our temporary access road, as we transport excavated soil and rock off-site.

    Our earthworks are about 90 per cent done. The high frequency truck movements should reduce by mid-June 2017, when the earthworks are expected to be completed.

    CPB Contractors have nearly completed their shotcrete (concrete sprayed through a specialised hose at high velocity) retaining wall works, which means the construction of concrete structures, including the tanks, will begin in the next month.

    Craigieburn Hub inlet structure
    The inlet structure is taking shape
    Craigieburn Hub - storage tank
    The ring beam excavation for storage tank 2 is complete

     

Map

Craigieburn Hub work area
The map above shows where works will occur

 

Timeline

Construction is scheduled to be completed in mid-2018.

CPB Contractors will work from Monday to Friday, between 6.00am and 6.00pm, and occasionally on Saturday between 6.00am and 5.00pm.

Contact us

If you have any questions or feedback please contact the project manager, Sally Crook, on 9872 2543.