Donnybrook Road East NDW Main Project

We’re building a new pipeline from Dwyer Street, Kalkallo to Langley Park Drive, Donnybrook to supply recycled water to housing development estates in the Northern Growth Area.

Our Project Partner, Comdain, will start construction in February 2022 and expect to be completed in late 2022, subject to weather and ground conditions.

The pipeline will be located within developer and privately-owned land as well as Hume and Whittlesea City Councils’ land and road reserves.

 

Donnybrook Road East_ NDW pipeline alignment
Donnybrook Road East NDW pipeline alignment 

What to expect

  • Normal working hours are expected to be 7.30am to 5.30pm Monday to Friday.
  • Our work will be noisy and dusty, especially when we cut the trench for the new pipes.
  • Some trees within the John Laffan Reserve will be removed, with approval from Hume City Council.
  • Comdain plan to establish a site office and storage area on vacant land in Ashbourne Boulevard, opposite Kinbrook Estate.
  • We don’t expect there’ll be any interruption to your services during these works.

We work to the latest State Government advice and have COVIDSafe plans in place. Our staff and project partners follow safe work practices in line with public health directions

Recycled water

For information about recycled water, link to www.yvw.com.au/help-advice/recycled-water

Project Updates

Download project fact sheet -January 2022

Contact us

For more information about this project, contact the Project Manager, Julian Wong, on 9872 1473 or email [email protected]