Sewerage Pumping Station Switchboard Upgrade Program

Currently, there are almost 90 sewerage pumping stations (SPSs) across our service district. These pump stations help to move raw sewage also known as wastewater to sewage treatment plants, via a network of underground pipes.

To improve the operational efficiency of our sewerage pumping stations, we plan to upgrade the switchboards at 10 sites. Each upgrade will be completed in stages as this will enable us and our contractors to work safely, within social distancing guidelines.

How do sewerage pumping stations work?

While most of our sewerage network is gravity-fed, there are some locations where a pumping station is required to transfer wastewater from a low point to a higher level so it can continue its journey to a treatment plant.

Pumping station

These pumping stations have:

  • an electrical switchboard for the power supply, pump controls and a communications mast, if required. The switchboard controls the automatic pump and remote monitoring system and provides a link to the underground pump cables in the chamber/wet well
  • a small, freshwater service cabinet that is used to clean the sewer pumps during maintenance, and for hygiene purposes by our maintenance crew
  • a concrete slab with safety guard rails and secured access lids. Underneath the slab is a chamber/wet well with pumps and valves
  • an electrical main switch/isolator cabinet that is located between the power distributor’s pole and the electrical switchboard. These cabinets are installed at our newer, upgraded sites.

Some locations have a generator onsite to enable the pump station to function during a power outage.

Find out more about how the sewerage system works

Visit information on Sewerage System

 

Where will we be doing upgrades?

SPS Switchboard location

Planned start date

SPS640 Yarra Boulevard, Kew

Completed 

View Newsletter

SPS641 River Retreat, Kew

Completed 

SPS179 Quambee Reserve, Ringwood North

Completed 

SPS177 Kimberley Drive, Lalor

April 2023 to October 2024

SPS206 Healesville Road, Woori Yallock

April 2023 to October 2024

SPS630 Victoria Road, Seville

April 2023 to October 2024

SPS631 Old Warburton Highway, Seville

April 2023 to October 2024

SPS638 Gateway West, Lilydale

April 2023 to October 2024

SPS668 Emerald Lake, Emerald

April 2023 to October 2024

SPS673 Sherriff Road, Emerald

April 2023 to October 2024

 

More information

If you have any questions or feedback about this project, please contact the Project Manager, Ed Zaid on 9872 1656 or by email [email protected]