Epping North Water Main Upgrade

We’re delivering a new water pipeline in Epping North to improve reliability of the local drinking water supply. 

As Melbourne’s north continues to grow, we need to upgrade our network to meet increasing demand.

The new 700-metre pipeline will work alongside the existing water main providing greater capacity and helping maintain water supply during maintenance or unexpected outages.

What's involved in the works?

Trenched construction

We’ll dig a narrow trench, lay the pipe, then backfill and restore the area once work is complete. This is the safest, simplest and most efficient way to install the pipe on open land. 

What to expect

  • Trucks, equipment and machinery on local roads.
  • Low to moderate levels of dust, noise and vibration. 

When will works start?

Construction will start in October 2026 and finish early 2027. We’ll use Harvest Home Road to enter and exit the access track onto the work site.

The pipeline will become operational once it’s connected to a new water main installed at the future Riverhills Estate.

Map of the North Epping Water Main Upgrade

Graphic map of Epping North Tank Outlet Duplication

Download map of the North Epping Water Main Upgrade (PDF, 4.2MB)

Contact us

For more information about this project please contact: 

Mohamed Ali, Yarra Valley Water Project Manager 
Phone: 03 9872 1431
Email: [email protected]